Crow Hall Lane Highways Update
Highway improvement works that are being carried out on and adjacent to Station Road roundabout, Cramlington. These works are a requirement to comply with the planning conditions of the development site on the A1171 (Crow Hall Lane). The work is split in to 3 phases, all requiring road closures. Phase 1 commenced in mid-July but has hit delays due to uncharted utilities at the new location of the northbound bus stop. Consequently, a re-design / solution has been required. This has now been resolved allowing the bus stop to be located in its new position and work has recommenced. If no other issues arise, phase 2 will commence on 07/11/22. Although the programme is delayed, Station Road roundabout will be free running throughout December until the new year to allow for the busy Christmas period. It is intended that work will continue off highway where traffic management is not required during this period.